TY - RPRT TI - The Port Fairy Pilot Wave Energy Project Environmental Management Plan AU - BioPower Systems AB - This Environmental Management Plan (EMP) details the environmental management requirements for the Port Fairy Pilot Wave Energy project.This EMP includes:The requirements for environmental management during the installation, operation and decommissioning activities;The responsibilities for implementing this EMP; andProject environmental controls and limits to ensure that project objectives and targets can be achieved with minimum impact on the environment.The Environmental Risk Register forms the basis for this EMP. It includes information on all activities which may have an impact on the environment, expected risk levels and controls, and limits to manage these risks. The approval of this EMP by the Director, Major Projects and Environmental Approvals Department of The Victorian Department of Environment, Land, Water & Planning (DELWP), is a condition of CM Act consent for the installation, operation, and decommissioning of the wave energy generator. BioPower Systems Pty Ltd (BPS) has responsibility for the project in accordance with the requirements of this EMP.BioWave Port Fairy Pilot Wave Energy Project DA - 2016/02// PY - 2016 SP - 38 PB - BioPower Systems SN - BPS-EMP-09-2016-2-2 UR - http://bps.energy/projects LA - English KW - Marine Energy KW - Wave KW - Environmental Impact Assessment ER -